Skyguide is moving into a new construction phase in a CHF 50 million renewal of its radar and radio site at La Dôle, in Switzerland’s Vaud Jura. A Heliswiss Super Puma has delivered 17 containers to the 1,677-metre summit to increase capacity for construction workers. The programme comprises about 15 projects and is expected to continue through 2039, while the site remains operational around the clock.
The work covers buildings, technical systems and the access cable car; the site’s last major refurbishment was about 40 years ago. Skyguide plans to improve fire and access protection, renovate buildings and upgrade technical infrastructure. A central resilience objective is to enable two buildings to operate independently, with separate power, cooling and radio equipment, so one can maintain critical functions if the other becomes unavailable.
The site supports radar surveillance and radio communications with flight crews. Its radar has a range of roughly 280 kilometres, covering traffic around Lyon, Milan and Zurich. Of the total budget, CHF 35 million is allocated to systems and infrastructure, with CHF 15 million for replacing the ageing cable car. The new installation is intended to transport heavy loads more readily and withstand wind, ice and cold better.
Mountain weather, restricted space and the current cable car’s limited capacity make construction slower than at lowland sites. Reporting on the project puts the additional time at about 50% to 60% compared with similar work at lower elevations.