The Saxon Higher Administrative Court has ruled that most challenges to the planned expansion of Leipzig/Halle Airport’s cargo facilities are unsuccessful, leaving a route for work on DHL’s apron to proceed once nature-protection assessments are corrected. The approval is unlawful and unenforceable in its current form, however, so construction cannot begin immediately. The court found that impacts on some bird species in two nearby protected areas had not been adequately assessed.
The plans include extending DHL’s apron by 39 hectares, adding taxiways, de-icing areas and operational buildings to increase capacity and accommodate newer, larger aircraft. Earlier estimates put the infrastructure investment at €300 million. DHL has operated its international express-freight hub at Leipzig/Halle since 2008; the airport is Germany’s second-largest cargo airport after Frankfurt.
The court rejected most other grounds raised by the ten claimants, including objections concerning aircraft noise, greenhouse-gas emissions and ultrafine particles. The group includes the Saxony and Saxony-Anhalt branches of environmental organisation BUND, the city of Schkeuditz, businesses and individuals. The cases were heard under references 7 C 34/24, 7 C 35/24 and 7 C 36/24.
The deficiencies can be addressed in supplementary proceedings. The court did not grant leave to appeal, but claimants may lodge a complaint after receiving the written reasons, which may take several months. The Federal Administrative Court in Leipzig would decide whether any appeal can proceed.